Congress Extends Streetcar Grant
Extended deadline for spending grant allows city to finish streetcar line through delayed Couture tower.
The $1.5 trillion spending bill signed into law Tuesday by President Joe Biden included some good news for Milwaukee’s streetcar system and Barrett Lo Visionary Development.
It keeps alive a 2015 grant program that is essential to the completion of The Hop’s lakefront spur. Without congressional action, Milwaukee was poised to lose the unspent portion of a $14.2 million grant that partially funds the construction of a streetcar extension through the base of The Couture.
Without the extension, the 2015 Transportation Investment Generating Economic Recovery (TIGER) program would have expired on Sept. 30, 2022. The extension keeps the program, and the city’s grant, alive for one more year.
“It was great news, but there is still more work to be done,” said a spokesperson for Acting Mayor Cavalier Johnson.
The Federal Transit Administration still needs to adjust its grant timeline, but the FTA has long been helpful to the city on the project. That included a 2021 extension that was to see the line enter service by June of this year.
Placing a streetcar stop in the base of The Couture, a 44-story, $190 million apartment tower, was a key piece of the pitch to secure the federal grant and for local officials to approve the streetcar.
But the tower, first proposed in 2012, has been repeatedly delayed. For years that didn’t impact the similarly-delayed streetcar, but by 2018 the timelines started to diverge. The city completed the system, including one-way lines on Michigan and Clybourn, but couldn’t open the lakefront extension alongside the rest of the system in November.
The day the system opened, developer Rick Barrett celebrated landing a key loan guarantee to advance the tower. But in the ensuing year the developer was unable to raise the additional funding necessary to access the guarantee. By 2020, Common Council members started pushing for an alternative plan to route the streetcar around the tower.
But come 2021, a solution seemed to be in sight. To access $19.5 million in public infrastructure funding from the city, Barrett and partner Tan Lo personally guaranteed the $1.41 million in unspent grant funds. A groundbreaking ceremony was held in June.
“As is expected with a major construction project on a 2-acre downtown site, there have been a few unforeseen conditions encountered while working below grade. In particular, we found two major discoveries that were not on the survey: more than 50 piles which needed to be identified and removed, and a We Energies transformer serving downtown which needed to be designed around. These challenges were addressed and construction is advancing,” said the developer in a February statement.
On Wednesday, Barrett confirmed a previously rumored issue: a dispute involving a wall on a neighboring building.
But all of that is now in the past according to Barrett and the city officials present for the start of a massive concrete pour.
“The predictability, from this day forward, we control and Findorff controls, and our subcontractors control,” said the developer. “When you have the unpredictability through the subsoil conditions, that’s always a really hard part and now we’re through that.”
The city expects to be given access to the site next year with enough time to put the streetcar line into service by September 2023. The council will need to approve a revised development agreement to better define that timeline.
When it’s completed, the line will operate east down E. Michigan St. and west down E. Clybourn St. A stop for both The Hop and the Milwaukee County East-West Bus Rapid Transit line will be included in the base of The Couture.
Photos
Renderings
More about the Couture
- The Couture Names First Retail Tenant - Sophie Bolich - Jun 6th, 2025
- Streetcar Begins Daily Service To The Couture, BRT Will Soon Follow - Jeramey Jannene - Apr 11th, 2024
- Friday Photos: See The View From The Couture’s Upper Levels - Jeramey Jannene - Mar 8th, 2024
- The Couture Shows Off First Apartments - Jeramey Jannene - Jan 24th, 2024
- Transportation: Streetcar Extension Opens Sunday - Jeramey Jannene - Oct 28th, 2023
- Lakefront Streetcar Extension Opens October 29 - Jeramey Jannene - Aug 22nd, 2023
- Eyes on Milwaukee: See Inside The Couture’s Rise - Jeramey Jannene - Mar 9th, 2023
- Transportation: Congress Extends Streetcar Grant - Jeramey Jannene - Mar 16th, 2022
- Eyes on Milwaukee: The Couture Starts Massive Concrete Pour - Jeramey Jannene - Mar 16th, 2022
- City Hall: Council Could End Fight Over Couture Provision - Jeramey Jannene - Feb 22nd, 2022
Read more about Couture here
More about the Milwaukee Streetcar
For more project details, including the project timeline, financing, route and possible extensions, see our extensive past coverage.
- FTA Tells Milwaukee to Crack Down on Fare Evasion — Even Where Fares Don’t Exist - Graham Kilmer - Dec 12th, 2025
- Alderman, State Allies Seek Federal Help to Kill the Streetcar - Jeramey Jannene - Oct 28th, 2025
- Streetcar Service Suspended Following Truck Crash - Jeramey Jannene - Oct 21st, 2025
- One Alderman’s Quest To Defund The Streetcar - Jeramey Jannene - Oct 18th, 2025
- Another Streetcar Collision - Jeramey Jannene - Jun 27th, 2025
- Streetcar Hit By Apparent Red Light Runner - Jeramey Jannene - Jun 16th, 2025
- Streetcar Will Run On Consolidated Route During Summerfest - Jeramey Jannene - Jun 11th, 2025
- City Hall: Milwaukee Must Replace Failing Streetcar Switches - Jeramey Jannene - Feb 24th, 2025
- Streetcar Confronts Limited Funding, Operations Challenges - Evan Casey - Jan 22nd, 2025
- Council Kills Streetcar’s ‘Festivals Line’ - Jeramey Jannene - Jul 31st, 2024
Read more about Milwaukee Streetcar here
Transportation
-
Congestion Pricing Cuts Air Pollution in New York City
Dec 14th, 2025 by Jeff Wood
-
FTA Tells Milwaukee to Crack Down on Fare Evasion — Even Where Fares Don’t Exist
Dec 12th, 2025 by Graham Kilmer
-
Will GOGO’s Bus Service Ever Get Going?
Dec 9th, 2025 by Jeramey Jannene