Deconstruction Contractor Delaying Work
City's program beset by delays. The latest is a contractor not showing up for work.
The idea behind deconstruction sounds simple. Instead of demolishing homes and sending the remains to a landfill, the city could create jobs, save the environment and possibly save money by having contractors with teams of entry-level employees dissemble or “deconstruct” homes with the materials being sold for reuse, offsetting the increased labor costs.
But the city’s experience is proving the concept anything but simple. A deconstruction ordinance was first approved in late 2017, but the city has now entered year two of a suspension of the requirement that private homeowners deconstruct properties, because high-priced contractor bids have made the program too expensive.
On the public side, the city has hired a private contractor, Spencer Renovation & Construction, to deconstruct 50 properties. After months of delays, described as “logjams with paperwork” by one alderman, that work got underway in November. A press conference with council members Robert Bauman, Milele A. Coggs and Russell W. Stamper, II was held inside the first home Spencer’s crew was deconstructing. Firm president Billy Spencer said his crew would disassemble a house every eight days, yielding up to $15,000 in materials.
“What seems to be the problem?” asked Alderman Robert Bauman at a meeting of the Joint Committee on Redevelopment of Abandoned and Foreclosed Homes.
“We can’t seem to get him to keep steadily working,” said DNS operations director Thomas G. Mishefske. He said Spencer has had his team performing privately-contracted work. “He’s not being very responsive to us.”
“A few days can go by with no one even there?” asked Bauman. Yes, said Mishefske.
DNS was scheduled to meet with Spencer on Friday. “He called earlier in the day, but didn’t show up for the meeting,” said DNS supervisor Chris Kraco.
Spencer is storing reclaimed materials at a Department of Public Works yard, and Mishefske said DNS would like to walk through it with him to see what he has in inventory. DNS said the non-profit Community Warehouse is interested in acquiring some of the materials. Spencer has also been selling the materials directly.
“Of course this behavior isn’t unheard of for contractors,” said Bauman of Spencer’s delays. The city, and a host of others in Wisconsin, have had poor experiences with contractors working on bridges delaying the projects to work on better-paying projects. Milwaukee, in response, has increased its penalties for delay.
What about penalties for delay in Spencer’s deal? Mishefske said there aren’t strict penalties, but DNS has divided the up-to $1.2 million contract into quarters. Spencer is scheduled to complete the first quarter and deconstruct 13 homes by April.
Spencer did not respond to a request for comment.
If you think stories like this are important, become a member of Urban Milwaukee and help support real, independent journalism. Plus you get some cool added benefits.
More about the Deconstruction Ordinance
- Amendment Would Shift Money From Demolishing Homes To Fixing Them - Jeramey Jannene - Oct 23rd, 2024
- Tentative Deal Would Salvage Milwaukee’s Deconstruction Program - Jeramey Jannene - Oct 25th, 2023
- Eyes on Milwaukee: Deconstruction Ordinance Again Suspended - Jeramey Jannene - Mar 17th, 2023
- Eyes on Milwaukee: Deconstruction Program Suspended Again - Jeramey Jannene - Feb 14th, 2022
- Eyes on Milwaukee: Deconstruction Policy Remains, Well… Deconstructed - Jeramey Jannene - Dec 13th, 2021
- Eyes on Milwaukee: New Deconstruction Firm Makes Progress - Jeramey Jannene - Feb 2nd, 2021
- Eyes on Milwaukee: City Hires New Deconstruction Contractor - Jeramey Jannene - Oct 12th, 2020
- Eyes on Milwaukee: City Moves to Fire Deconstruction Firm - Jeramey Jannene - Mar 2nd, 2020
- Eyes on Milwaukee: Deconstruction Contractor Delaying Work - Jeramey Jannene - Jan 27th, 2020
- Eyes on Milwaukee: City Deconstruction Delayed Through 2020 - Jeramey Jannene - Jan 14th, 2020
Read more about Deconstruction Ordinance here
Eyes on Milwaukee
-
Church, Cupid Partner On Affordable Housing
Dec 4th, 2023 by Jeramey Jannene -
Downtown Building Sells For Nearly Twice Its Assessed Value
Nov 12th, 2023 by Jeramey Jannene -
Immigration Office Moving To 310W Building
Oct 25th, 2023 by Jeramey Jannene