The Couture Starts Massive Concrete Pour
78 truckloads of concrete for building's base. Developer exploring direct link to US Bank complex.
A key construction milestone was reached Wednesday on The Couture, a 44-story apartment tower under construction at 909 E. Michigan St.
A concrete pour was initiated to support the tower. A nearly continuous pour from two pumps will last approximately six hours, supplied by 78 truckloads of concrete from Riv/Crete.
Acting Mayor Cavalier Johnson, Department of City Development Commissioner Lafayette Crump and Interim Public Works Commissioner Karen Dettmer joined developers Rick Barrett and Tan Lo to watch the start of the pour.
“It’s not just about Downtown,” but jobs, said Johnson. He noted the city’s Residents Preference Program will ensure that at least 40% of the project’s work hours are performed by unemployed or underemployed city residents. Barrett Lo Visionary Development is subject to the program because the city is providing $19.5 million for public infrastructure costs related to the project, including a transit concourse for the streetcar and bus rapid transit line.
There have been approximately 25 people on site daily in recent weeks, a long way from the hundreds expected to arrive later this year. The building is expected to take more than one million work hours to complete.
The developer is excited that people will be able to see the building at its peak height, planned to be approximately 517 feet, in a year.
“We are going to top off this building a year from today,” said Barrett, ever the optimist. Findorff senior project manager Eric Sadler said it wouldn’t happen until summer 2023.
Regardless of when it happens, Barrett is already looking past that. He said model units would be available in fall 2023 and the first residents could move in by “late 2023.”
The building wouldn’t be completely finished at that point. Instead, floors four through 19 would open for residents, with a temporary roof installed above the 19th floor to allow open-air work to continue above without impacting the residents below.
The base of the building, including the underground parking structure and three-story transit and retail concourse, will take longer to pour and form the concrete to be used. Then things will accelerate. “Floors five through 44 will have one floor every four days,” said Barrett.
The $190 million building will include 312 high-end apartments, approximately 45,000 square feet of retail space and 500 parking spaces.
Barrett didn’t have any news to share on the retail leasing Wednesday, other than to say discussions continue are ongoing. “We are working hard behind the scenes,” he said.
But there is a potential new amenity coming to the tower.
Skywalk To US Bank Center Complex
Following the resolution of an issue with a wall that separates the development from the adjacent 833 East office tower, Barrett is exploring a skywalk connection with Irgens‘ 18-story office building.
“Ideally, we are trying to do it elevated through a glass entrance,” said Barrett. “We would like to do it in a handsome way.”
The connection with 833 East would also provide direct access to the US Bank Center, The Westin Milwaukee hotel and a series of other nearby office buildings. People could walk from the transit concourse into any of the other buildings without having to step outside.
A 13-foot-tall wall on the eastern edge of Irgens’ property was cited by Barrett as one of the factors that delayed The Couture’s construction progress. He said it was a remnant of the building Irgens replaced with its 2016 building and was sitting on the foundation site for The Couture. Irgens has previously expressed concern that additional development at The Couture site could negatively impact its building.
“Our relationship has really grown and maybe we can get something done,” said Barrett. “We are trying to figure that out right now.”
Barrett said he had difficulty sleeping because of the issues that could occur underground. And plenty did: the Irgens wall, We Energies equipment, a sewer relocation and other conditions were cited as causes of delay for the project.
“The predictability from this day forward we control and Findorff controls, and our subcontractors control,” said the developer. “When you have the unpredictability through the subsoil conditions, that’s always a really hard part and now we’re through that.”
Photos
Renderings
More about the Couture
- Streetcar Begins Daily Service To The Couture, BRT Will Soon Follow - Jeramey Jannene - Apr 11th, 2024
- Friday Photos: See The View From The Couture’s Upper Levels - Jeramey Jannene - Mar 8th, 2024
- The Couture Shows Off First Apartments - Jeramey Jannene - Jan 24th, 2024
- Transportation: Streetcar Extension Opens Sunday - Jeramey Jannene - Oct 28th, 2023
- Lakefront Streetcar Extension Opens October 29 - Jeramey Jannene - Aug 22nd, 2023
- Eyes on Milwaukee: See Inside The Couture’s Rise - Jeramey Jannene - Mar 9th, 2023
- Transportation: Congress Extends Streetcar Grant - Jeramey Jannene - Mar 16th, 2022
- Eyes on Milwaukee: The Couture Starts Massive Concrete Pour - Jeramey Jannene - Mar 16th, 2022
- City Hall: Council Could End Fight Over Couture Provision - Jeramey Jannene - Feb 22nd, 2022
- Eyes on Milwaukee: The Couture Completion Delayed Until End of 2023 - Jeramey Jannene - Feb 3rd, 2022
Read more about Couture here
Political Contributions Tracker
Displaying political contributions between people mentioned in this story. Learn more.
- April 22, 2019 - Cavalier Johnson received $50 from Lafayette Crump
Eyes on Milwaukee
-
Church, Cupid Partner On Affordable Housing
Dec 4th, 2023 by Jeramey Jannene -
Downtown Building Sells For Nearly Twice Its Assessed Value
Nov 12th, 2023 by Jeramey Jannene -
Immigration Office Moving To 310W Building
Oct 25th, 2023 by Jeramey Jannene