25-Hour, 670-Load Concrete Pour for BMO Tower

New office tower will start to climb upwards after 13,980 tons of concrete are put down.

By - Jun 2nd, 2018 01:55 pm
BMO Tower Concrete Pour. Photo by Jeramey Jannene.

BMO Tower Concrete Pour. Photo by Jeramey Jannene.

Despite that it’s more than a year from opening, the site of the BMO Tower is going to be quite busy this weekend.

Concrete mixers will line E. Wells St. virtually all weekend as a 25-hour concrete pour is underway to build the foundation for the 25-story office tower.

Once the clock struck midnight on Saturday morning, crews from building general contractor J.H. Findorff & Son and concrete supplier began the process of pouring 13,980 tons of concrete into a hole in the ground at the corner of N. Water St. and E. Wells St. Approximately 40 workers will be on site at any given moment for the duration of the pour.

Where does all of the concrete come from? In this case it’s coming from Ozinga facilities in nearby Oak Creek and West Allis. Drivers will supply 6,700 yards of concrete, the biggest pour since Northwestern Mutual‘s 10,000-cubic-yard pour in April 2015.

Drivers will make 670 trips by the time the process wraps up Sunday morning, with a new vehicle arriving every two to three minutes. Helping support that concrete is 84 miles of rebar weighing 580 tons.

The foundation has an estimated cost of $2 million.

The 359,920 square-foot tower will replace the now-demolished 417-stall parking garage at 790 N. Water StBMO Harris Bank, which acquired M&I Bank in 2011, will occupy 123,000 square-feet in the tower, spread over floors 11 through 15, with a flagship, two-story bank branch on the corner of N. Water and E. Wells streets. Law firm Michael Best & Friedrich will lease 59,000 square-feet of space spread across two-and-a-half floors at the top of the tower. An eight-level parking garage at the base of the tower will include 647 parking spaces.

Irgens Partners is developing the $132 million project. Kahler Slater is serving as the project architect.

As part of big redevelopment scheme, Irgens will also redevelop the existing, 21-story BMO office building. That part of the project won’t start until 2020 at the earliest. Developer Mark Irgens has suggested a mix of uses could be included in the overhauled tower, including workforce housing, a hotel or office space.

BMO has approximately 700 employees in their current tower, and another 200 in the nearby Milwaukee Center. Both groups will relocate to the new building.

The new tower will feature a number of amenities, including a shared multi-media conference center, common tenant lounge and terrace on the 12th floor. BMO will have a private outdoor terrace on the 11th floor and Michael Best will have one on the 25th floor. A tenant fitness center will be constructed underground with lots of light, private showers and locker rooms.

Photos

Renderings

Plans

If you think stories like this are important, become a member of Urban Milwaukee and help support real independent journalism. Plus you get some cool added benefits, all detailed here.

Leave a Reply

You must be an Urban Milwaukee member to leave a comment. Membership, which includes a host of perks, including an ad-free website, tickets to marquee events like Summerfest, the Wisconsin State Fair and the Florentine Opera, a better photo browser and access to members-only, behind-the-scenes tours, starts at $9/month. Learn more.

Join now and cancel anytime.

If you are an existing member, sign-in to leave a comment.

Have questions? Need to report an error? Contact Us