State Quietly Expands I-94 Project
Reconstruction of I-94 would extend 23% further into city, stretching east to 16th Street, WISDOT says.
The Wisconsin Department of Transportation this week quietly moved the eastern boundary of the I-94 east-west reconstruction and expansion project from 25th St. to 16th St., extending the project by 23 percent.
WisDOT’s extension increases the project length from 2.85 miles to 3.5 miles, a increasing it by.65 miles. Cost figures were not included in the announcement, which was made in the Federal Register.
All of its I-94 reconstruction public outreach, including a total of eight public meetings, dealt with a project that ended at 25th St.
Said WisDOT in its Federal Register announcement: “Public involvement is a critical component of the National Environmental Policy Act (NEPA) project development process and will continue to occur throughout the development of the EIS (environmental impact statement).”
The agency said the expanded project area “is in response to additional work necessary east of 25th Street to accommodate alternatives that would tie back into I-94 near 16th Street and better match the recently reconstructed Marquette Interchange.”
WisDOT did not explain why those two things were not considered since the start of the I-94 planning.
WisDOT said it would respond “soon” to inquiries about the expanded project area and has plans for new public outreach efforts.
If you think stories like this are important, become a member of Urban Milwaukee and help support real, independent journalism. Plus you get some cool added benefits.
More about the I-94 East-West Expansion
- Transportation: Fix At Six Coalition Sues State, Federal Government Over I-94 Expansion - Graham Kilmer - Aug 20th, 2024
- WisDOT to host I-94 East-West Freeway Project public meetings - Wisconsin Department of Transportation - Jun 12th, 2024
- Open Houses Announced For I-94 Widening - Jeramey Jannene - Jun 6th, 2024
- ‘Fix at Six’ Group Wants I-94 Expansion Delayed For Civil Rights Report - Jeramey Jannene - Mar 20th, 2024
- Coalition Admonishes I-94 expansion Record of Decision - Sierra Club - Mar 20th, 2024
- Feds Approve Interstate 94 Expansion - Jeramey Jannene - Mar 8th, 2024
- Advocates condemn approval of I-94 expansion - Sierra Club - Mar 8th, 2024
- I-94 East-West Project Receives Federal Approval - Wisconsin Department of Transportation - Mar 8th, 2024
- Federal Government Investigating Civil Rights Complaint About I-94 Expansion - Evan Casey - Jan 11th, 2024
- Op Ed: 8-Lane I-94 Expansion Is Worst for Carbon Emissions - Cassie Steiner, Cheryl Nenn and Terry Wiggins - Dec 18th, 2023
Read more about I-94 East-West Expansion here
The Marquette interchange was altered since the original plan… doesn’t it make sense to then alter these plans because of the changes to the interchange? We’ll see if that’s true once further explanation is given, but that’s what makes sense to me right off the bat.
Does “extending the project by 23 percent” mean an extension of miles or dollars?
@Dave K Miles… The dollar amount has not been revealed yet.
Any extension to the project footprint requires either an addendum to or the complete reissuance of a NEPA EIS, including new public hearings.
@Ann S Correct. WisDOT has put in an Revised Notice of Intent To Prepare an Environmental Impact Statement: Milwaukee County, Wisconsin
https://www.federalregister.gov/articles/2013/08/28/2013-20964/revised-notice-of-intent-to-prepare-an-environmental-impact-statement-milwaukee-county-wisconsin
If I had to guess, there was a major issue with traffic numbers that required additional local road improvements east of the initial proposed tieback. Once the EIS develops to a certain point, usually after the conclusion of the relatively arduous public hearing process, designers have it hammered into their heads to under no circumstances alter the footprint because it leads to situations like this. Again, just a totally uninformed guess, but a somewhat-educated one.
Yes, by all means, save those cars and SOVs 20 seconds of travel time at the expense of the adjacent neighborhoods. Pay no attention to decreasing VMTs, static population growth, or growing trend data indicating that younger generations care less about driving. Expand that concrete and asphalt! Expand it all!
Does the existing contractor automatically get the additional revenue generated by the extra mileage? Is it possible that this extension is a giveaway to a particular road builder?