Foxconn No Longer Needs Lake Michigan Water?
Environmentalists say company doesn’t need permit to withdraw 7 million gallons per day.
An environmental law center suing the state Department of Natural Resources over the decision to divert water to Foxconn Technology Group for its manufacturing plant says the company’s change of plans should put the water diversion on hold.
Midwest Environmental Advocates in May challenged the DNR’s approval of a city of Racine request to divert 7 million gallons of water per day outside the Great Lakes Basin.
Sarah Geers, an attorney with the group, said the reason that Foxconn needed so much water was to manufacture LCD screens. This week, Reuters reported Foxconn might be moving away from manufacturing television screens and would instead focus on engineering and development.
“Plans for the site have changed in fundamental ways since this project was first pitched to the public,” Geers said. “In light of these dramatic changes, we are carefully evaluating how Foxconn’s new plans affect the city of Racine’s planned diversion of Great Lakes water.”
A DNR spokesman said the department hasn’t received a request to modify or rescind the diversion approval so it remains valid.
Geers said she expects a decision within the next few months.
The Midwest Environmental Advocates filed a legal action under the Great Lakes Compact in May. The group is representing six entities: Milwaukee Riverkeeper, League of Women Voters of Wisconsin, League of Women Voters Lake Michigan Region, River Alliance of Wisconsin, Natural Resources Defense Council and Minnesota Center for Environmental Advocacy.
Meanwhile, a Washington, D.C.-based nonpartisan research group, Good Jobs First, weighed in on the Foxconn changes.
Greg LeRoy, who heads the organization, said the DNR should immediately stop the water diversion in light of the most recent Foxconn news.
“Struck me as unusual to begin with and any environmentalist should be concerned,” LeRoy said. “And now, presumably, the company won’t need that waiver. The question is how much the county and the local authorities (have) already paid for the infrastructure. They should make them whole.”
Listen to the WPR report here.
Environmentalists Say Foxconn No Longer Needs Lake Michigan Water Diversion was originally published by Wisconsin Public Radio.
More about the Foxconn Facility
- Mount Pleasant, Racine in Legal Battle Over Water After Foxconn Failure - Evan Casey - Sep 18th, 2024
- Biden Hails ‘Transformative’ Microsoft Project in Mount Pleasant - Sophie Bolich - May 8th, 2024
- Microsoft’s Wisconsin Data Center Now A $3.3 Billion Project - Jeramey Jannene - May 8th, 2024
- We Energies Will Spend $335 Million on Microsoft Development - Evan Casey - Mar 6th, 2024
- Foxconn Will Get State Subsidy For 2022 - Joe Schulz - Dec 11th, 2023
- Mount Pleasant Approves Microsoft Deal on Foxconn Land - Evan Casey - Nov 28th, 2023
- Mount Pleasant Deal With Microsoft Has No Public Subsidies - Evan Casey - Nov 14th, 2023
- Microsoft, State Announce Massive Data Center Expansion, Land Purchase - Joe Schulz - Nov 11th, 2023
- Gov. Evers Announces Microsoft Makes Major Investment in Wisconsin - Gov. Tony Evers - Nov 10th, 2023
- State Can’t Regulate We Energies $100 Million Project for Microsoft - Joe Schulz - Sep 20th, 2023
Read more about Foxconn Facility here