Lane closures and traffic shifts planned along I-894 for median work
Part of ongoing I-894 rehabilitation project in Milwaukee County.
WisDOT is notifying motorists of upcoming, long-term traffic shifts and lane closures along I-894 in Milwaukee County. These shifts will allow construction crews to begin median reconstruction work along the corridor.
What to Expect
Beginning Thursday, March 14:
- The left lane on westbound I-894 (northbound I-41 within Mitchell Interchange), between Layton Avenue and 85th Street, is scheduled to close until mid-summer.
- Eastbound and westbound traffic on I-894, between 92nd Street and 27th Street, will be shifted to the outside shoulders until mid-summer.
Beginning Monday, March 18:
- The left lane on eastbound I-894 between Cold Spring Road and 92nd Street (Hale Interchange) is scheduled to close for approximately one month.
All work is weather dependent and subject to change.
These lane closures and traffic shifts are part of the ongoing rehabilitation project on I-894 between 84th and 35th Streets.
Learn more about the project here: https://projects.511wi.gov/894/
NOTE: This press release was submitted to Urban Milwaukee and was not written by an Urban Milwaukee writer. While it is believed to be reliable, Urban Milwaukee does not guarantee its accuracy or completeness.
Mentioned in This Press Release
Recent Press Releases by Wisconsin Department of Transportation
Put Safety First During Labor Day Weekend Travel
Aug 26th, 2025 by Wisconsin Department of TransportationExpect company on Wisconsin roads and “know before you go” with 511wi.gov
Upcoming Long-Term System Ramp Closures in the Hale Interchange
Aug 21st, 2025 by Wisconsin Department of TransportationAs part of the ongoing I-41/43/894 and Hale Interchange resurfacing project in Milwaukee County, the Wisconsin Department of Transportation (WisDOT) is notifying motorists of upcoming impacts scheduled to begin after Labor Day.