Harbor Commission Approves Massive Cleanup Facility
New 42-acre, MMSD facility on lake could store 1.9 million cubic yards of sediment
A proposal to make Milwaukee waterways substantially cleaner involves shrinking Lake Michigan by 42 acres.
The Milwaukee Metropolitan Sewerage District is leading the construction of a new facility that would stick out into the lake near the southern end of the Hoan Bridge. Known as the Dredged Material Management Facility (DMMF), it would be capable of storing 1.9 million cubic yards of sediment.
The facility is to store sediment removed from the area’s waterways as part of a federally-backed effort to remove the “Area of Concern” (AOC) designation that was first given to the area in 1987 because of historical environmental contamination.
The cleanup effort, now known as the Waterway Restoration Partnership, was first announced in January 2020 and is expected to cost hundreds of millions of dollars. A February press release from MMSD says the project partners hope to leverage $260 million in federal resources as part of the larger project. It’s expected the cleanup will take six years to complete and involve the removal of metals, polychlorinated biphenyls (PCBs), polynuclear aromatic hydrocarbons (PAHs) and other pollutants.
The Board of Harbor Commissioners took its first formal votes on the multi-agency project last week Thursday.
The City of Milwaukee, through the Harbor Commission, will eventually own the facility, similar to a federally-funded facility to the south. That earlier facility, the 50-acre Confined Disposal Facility (CDF) from 1975, is partially leased to the Lake Express as a ferry terminal and another portion houses South Shore Cruise Dock. The northernmost portion of the CDF, approximately 30 acres in size, is not completely full and will be used at the start of the AOC cleanup in 2023 for a We Energies contamination cleanup of the Milwaukee River near the Historic Third Ward.
On Thursday the commission unanimously approved two things: allowing MMSD to use the city’s submerged land grant authority from the state to build the facility and a financial contribution to the DMMF’s further design and engineering.
Approximately $100,000 would go towards the final design and permitting costs for the facility. Tindall-Schlicht said the amount is “5% to 10% of the design costs.” Ramboll, an engineering consultancy, is leading the final design. Tindall-Schlicht said We Energies, which led the initial design, is now largely out of the process.
“Much more ahead with the [cleanup]. It’s going to be a generational project,” said Tindall-Schlicht.
“Well we spent 150 years messing it up,” said commissioner Ron San Felippo to laughter.
The construction of a storage facility is seen as a cost-effective strategy by the project partners. It avoids the need to first process and dry the sediment, eliminates tens of thousands of truck trips to haul the sediment and avoids the tipping fees associated with disposing of the material.
But paradoxically, before it’s even built it’s already full on paper. Of the 1.9 million cubic yard capacity, 1.4 million is dedicated to the Environmental Protection Agency cleanup, with MMSD (300,000) and the port (200,000) getting the additional capacity for planned projects decades into the future.
An unplanned project could arrive in 2027 and make matters tighter.
Port Milwaukee chief engineer Brian Kasprzyk said expanding the facility’s footprint wasn’t a viable option. “We are pretty much at the maximum size we can fit in there,” he told the board. The reason is the location. The shipping lanes in the port skirt the edge of the planned facility, which would stick out about as far as the nearby piers.
The DMMF was estimated to cost $96 million when the Wisconsin State Legislature approved a proposal to allow MMSD to temporarily exceed its borrowing cap to fund the project. But project documents now estimate the cost could reach $150 million. MMSD will pay for a portion of the project using an EPA loan fund.
What did Milwaukee do with dredged material before building storage facilities? Took it out into the lake and dumped it into deep areas.
The Milwaukee Estuary Area of Concern encompasses the Inner Harbor and Milwaukee, Menomonee and Kinnickinnic rivers. The area is roughly bounded by E. North Ave. to the north, W. Cleveland Ave. to the south, Lake Michigan to the east and N. 35th St. to the west. An expanded area of concern includes the Milwaukee River to Cedarburg, the Little Menomonee River almost to the Mequon border, and the Kinnickinnic River to Greenfield.
There are five Areas of Concern in Wisconsin and 43 designated Areas of Concern in the Great Lakes, including 17 in Canada and seven shared by the US and Canada.
Future uses of the DMMF site will need to comply with the Public Trust Doctrine.
If you think stories like this are important, become a member of Urban Milwaukee and help support real, independent journalism. Plus you get some cool added benefits.
More about the Area of Concern Abatement Effort
- MKE County: County Deploying $1.3 Million in Environmental Cleanup Grants - Graham Kilmer - Sep 19th, 2024
- MKE County: Habitat Restoration Coming to Kohl Park - Graham Kilmer - Jan 12th, 2024
- MKE County: Largest Fish Barrier Between Grafton and Lake Michigan Removed - Graham Kilmer - Dec 21st, 2023
- EPA Giving Milwaukee $17 Million For Sewer Project - Evan Casey - Nov 2nd, 2023
- Cleanup Of Polluted Great Lakes Sites Reverses Housing Price Declines - Danielle Kaeding - Oct 19th, 2023
- Milwaukee Wins $275 Million Grant To Fund Massive Waterway Cleanup - Jeramey Jannene - Oct 12th, 2023
- MKE County: Parks Restoring Wildlife Habitat in Little Menomonee River Parkway - Graham Kilmer - Sep 13th, 2023
- What’s That Orange Barrier in the Milwaukee River? - Jeramey Jannene - May 9th, 2023
- ‘Living Breakwater’ Would Protect Harbor - Jeramey Jannene - Mar 8th, 2023
- MKE County: County Planning Habitat Restoration in Milwaukee River Greenway - Graham Kilmer - Jan 13th, 2023
Read more about Area of Concern Abatement Effort here
Eyes on Milwaukee
-
Church, Cupid Partner On Affordable Housing
Dec 4th, 2023 by Jeramey Jannene -
Downtown Building Sells For Nearly Twice Its Assessed Value
Nov 12th, 2023 by Jeramey Jannene -
Immigration Office Moving To 310W Building
Oct 25th, 2023 by Jeramey Jannene