The Foxconn Real Estate Show
There are now four buildings on Mount Pleasant campus. But what exactly are they for?
More than three and a half years after Foxconn signed a memorandum with Gov. Scott Walker promising to turn Racine County into the Silicon Valley of Wisconsin, the company still isn’t manufacturing anything. Other than press releases.
But it continues to put up buildings. As one Foxconn employee told The Verge, in describing the utter failure of the project in Racine County: “When you’re desperate and you have no product to sell and the only asset you have is land, what can you do? You build on it or you grow crops on it.”
The company’s original promise was to create 20 million square feet of manufacturing, prompting former President Donald Trump to dub the project “the eighth wonder of the world.” Alas, it has fallen far short, at about 2% of the promised footprint. But it has created four different buildings that some day may be useful for something. The list includes:
(1) The Multipurpose Building. The 120,000-square-foot building is the first structure built on the campus by Foxconn, in 2018, probably to show some progress as Walker ran for reelection and the company began changing its mind about what it might manufacture. The general contractor for the building was joint venture of M+W Group and Gilbane Building Co., and Foxconn declared that 37 contractors in the state were hired to help build it. As for its purpose: “It will house research and development facilities focusing on advanced display technology and applications in all aspects of smart lives,” the company said, and “will contribute to the development of the AI 8K+5G ecosystem that Foxconn is building across the Badger State.” None of that has happened, either in Mount Pleasant or across the state. But this building has been the main site of what little activity has happened on the campus.
(2) The Fab. This was supposed to be the big one. Foxconn had promised a Gen 10.5 fabrication manufacturing facility, then cut that down to a Gen 6 fabrication facility. Ground was broken for the facility in the summer of 2018 and then the delays began. One year later the company announced that Foxconn and its construction manager, Gilbane | Exyte “began the concrete foundations and footing pour for the 988,999 square-foot” facility that would become “the first and only thin-film-transistor liquid-crystal display (TFT-LCD) advanced manufacturing facility in North America.”
In January 2020 the company announced it had completed the roof installation and weathertight enclosure of the building in a press release that now described it as an “Advanced Manufacturing Center.” There was no mention of LCD fabrication. Nor was there any mention of what might be manufactured there. It remains little more than an empty shell.
(3) Smart Manufacturing Center. In September 2019, Foxconn announced it had selected Mortenson to serve as Construction Manager for a Smart Manufacturing Center it would build. The 260,000-square-foot facility “will be a high-mix, low-to-medium volume production facility that primarily manufactures components for server racks,” a company new release promised. Some 16 months later the company announced that “vertical construction and steel placement is underway” for the facility. But the building now had an added purpose: “to further attract business partnerships within the WVSTP,” or Wisconn Valley Science and Technology Park. as Foxconn has dubbed its Mount Pleasant campus.
Have any of those partnerships happened? Well, Foxconn announced it would be making airport coffee houses with the Briggo company back in September 2019, but nothing has come of that. And in April 2020 Foxconn announced it would be making ventilators in a partnership with Medtronic, with a with a goal of manufacturing 400 ventilators per week by the end of April and 700 per week by May 2020. But last week Medtronic told reporter Ricardo Torres the deal was off due to a “lack of demand.”
As for those data server racks, Foxconn promised they were coming in a November 2020 Op Ed at the same time it appears to have floated a rumor it would be building these for Google. But Google never confirmed this and there is still no announced partner for this, or for any other project at the Smart Manufacturing Center.
(4) The Globe. In September 2019 Foxconn announced it would build a nine-story circular office building reminiscent of Epcot’s iconic Spaceship Earth building at the entrance of its Orlando theme park. One day later Foxconn announced it wasn’t going to build this. Whoops. Bad start.
Foxconn’s latest announcement, reported by the Wall Street Journal, is that it will partner with the California startup company Fisker to build electric cars. While it’s assumed the cars would be built at Mount Pleasant, Foxconn has yet to confirm that it will. Not to mention that the electric car business has become incredibly competitive and anything but a sure prospect for a startup company. And in any case the production is not expected to happen until the fourth quarter of 2023 — more than six years after Foxconn signed its MOU with Walker.
Given that none of its buildings are manufacturing anything, why does Foxconn keep adding more facilities? Because its contract with Mount Pleasant and Racine County requires that Foxconn create at least $1.4 billion in new property value by Jan. 1, 2023. And its last assessment, in January 2020, showed the total value of all its property at $260.6 million.
Which I guess means we’ll continue to see more real estate announcements, adding more unneeded buildings to the most unnecessary manufacturing campus in the world.
If you think stories like this are important, become a member of Urban Milwaukee and help support real, independent journalism. Plus you get some cool added benefits.
More about the Foxconn Facility
- Mount Pleasant, Racine in Legal Battle Over Water After Foxconn Failure - Evan Casey - Sep 18th, 2024
- Biden Hails ‘Transformative’ Microsoft Project in Mount Pleasant - Sophie Bolich - May 8th, 2024
- Microsoft’s Wisconsin Data Center Now A $3.3 Billion Project - Jeramey Jannene - May 8th, 2024
- We Energies Will Spend $335 Million on Microsoft Development - Evan Casey - Mar 6th, 2024
- Foxconn Will Get State Subsidy For 2022 - Joe Schulz - Dec 11th, 2023
- Mount Pleasant Approves Microsoft Deal on Foxconn Land - Evan Casey - Nov 28th, 2023
- Mount Pleasant Deal With Microsoft Has No Public Subsidies - Evan Casey - Nov 14th, 2023
- Microsoft, State Announce Massive Data Center Expansion, Land Purchase - Joe Schulz - Nov 11th, 2023
- Gov. Evers Announces Microsoft Makes Major Investment in Wisconsin - Gov. Tony Evers - Nov 10th, 2023
- State Can’t Regulate We Energies $100 Million Project for Microsoft - Joe Schulz - Sep 20th, 2023
Read more about Foxconn Facility here
Murphy's Law
-
National Media Discovers Mayor Johnson
Jul 16th, 2024 by Bruce Murphy -
Milwaukee Arts Groups in Big Trouble
Jul 10th, 2024 by Bruce Murphy -
The Plague of Rising Health Care Costs
Jul 8th, 2024 by Bruce Murphy
With 3.2 billion dollars in taxpayers money invested and nothing happing, there needs to be an investigation. This taxpayer ripoff is either a product of intentional misrepresentation by Foxconn, malfeasance by the Republican officials who negotiated the contract, or some entity bribing State officials. One can also wonder if there was some future payback for Trump’s business dealings in China.