Foxconn Technology Group began construction Monday on its long-awaited manufacturing plant in Racine County. It marks the beginning of what will be a nearly 1 million-square-foot plant the Taiwan-based company is calling its Gen 6 Fab building.
Foxconn’s plans have changed several times since announcing its intent to build flat screens in Wisconsin in 2017 with a 22 million-square-foot Gen 10 plant. Foxconn officials said market changes prompted the company to shift to a smaller Gen 6 facility.
This building is where smaller screens for cell phones and iPads will be manufactured. Originally, Foxconn planned to make television screens in Wisconsin.
Foxconn representatives could not be reached for comment but have said the facility would be operational by the end of 2020.
So far, only a single building on the campus has been completed — a 120,000-square-foot multi-purpose facility that opened in late 2018.
Last month, Gov. Tony Evers told CNBC he met with Foxconn and now has “clarity” on the project. Evers predicts Foxconn will hire 1,500 people in 2020. That’s compared to 1,800 under the plan the company laid out, which would eventually hire up to 13,000 workers in the state.
Foxconn representatives have repeatedly said they will meet hiring goals.
Listen to the WPR report here.
Foxconn Goes Vertical On Mount Pleasant Project was originally published by Wisconsin Public Radio.
More about the Foxconn Facility
- Mount Pleasant, Racine in Legal Battle Over Water After Foxconn Failure - Evan Casey - Sep 18th, 2024
- Biden Hails ‘Transformative’ Microsoft Project in Mount Pleasant - Sophie Bolich - May 8th, 2024
- Microsoft’s Wisconsin Data Center Now A $3.3 Billion Project - Jeramey Jannene - May 8th, 2024
- We Energies Will Spend $335 Million on Microsoft Development - Evan Casey - Mar 6th, 2024
- Foxconn Will Get State Subsidy For 2022 - Joe Schulz - Dec 11th, 2023
- Mount Pleasant Approves Microsoft Deal on Foxconn Land - Evan Casey - Nov 28th, 2023
- Mount Pleasant Deal With Microsoft Has No Public Subsidies - Evan Casey - Nov 14th, 2023
- Microsoft, State Announce Massive Data Center Expansion, Land Purchase - Joe Schulz - Nov 11th, 2023
- Gov. Evers Announces Microsoft Makes Major Investment in Wisconsin - Gov. Tony Evers - Nov 10th, 2023
- State Can’t Regulate We Energies $100 Million Project for Microsoft - Joe Schulz - Sep 20th, 2023
Read more about Foxconn Facility here