Incidental Take Notice For Rock County
MADISON, Wis. – The Wisconsin Department of Natural Resources (DNR) proposes to issue an authorization for the incidental taking of a rare turtle, which may result from the Rock County Reliability Project.
Incidental take refers to the unintentional loss of individual endangered or threatened animals or plants that does not put the species’ overall population at risk.
The Kittyhawk Substation expansion work will require development of an existing upland fallow field, and the proposed X-126 transmission line occurs primarily within existing industrial developed land associated with the Riverside and West Riverside Energy Centers. The existing and proposed X-23 and Y-72 right-of-ways (ROW) traverse the Rock River, Rock River riparian wetland complex including cleared and uncleared forested and shrub wetlands and herbaceous wetlands, maintained WisDOT right-of-ways, agricultural fields, farmed wetlands, cleared and uncleared wooded uplands and grassland areas. The areas of proposed right-of-way expansion along X-23 east of Hwy 51 include similar land cover. The project also includes off right-of-way access routes and laydown yards which are associated with existing gravel quarries, gravel roads and otherwise developed areas. No clearing is anticipated along the off right-of-way access routes or for the laydown yards.
The presence of the state endangered ornate box turtle is confirmed in the vicinity of the project site. DNR staff determined that the proposed project may result in the incidental taking of some turtles.
The DNR concludes that the proposed project will minimize the impacts to the species by adhering to conservation measures; is not likely to jeopardize the continued existence and recovery of the state population of the species or the whole plant-animal community of which it is a part; and has benefit to the public health, safety or welfare that justifies the action.
Conservation measures to minimize the adverse effect on the endangered species will be incorporated into the proposed Incidental Take Authorization. Copies of the jeopardy assessment and background information on the ornate box turtle are available by visiting the DNR Incidental Take Public Notices webpage or upon request from DNR Conservation Biologist Stacy Rowe at stacy.rowe@wisconsin.gov or 608-228-9796.
The public is encouraged to submit written comments regarding project-related impacts to the ornate box turtle by July 19, 2023 to:
Department of Natural Resources
c/o Stacy Rowe, DNR Conservation Biologist
2514 Morse St.
Janesville, WI 535450
stacy.rowe@wisconsin.gov or 608-228-9796
NOTE: This press release was submitted to Urban Milwaukee and was not written by an Urban Milwaukee writer. While it is believed to be reliable, Urban Milwaukee does not guarantee its accuracy or completeness.
Mentioned in This Press Release
Recent Press Releases by Wisconsin Department of Natural Resources
DNR Seeking Public Comment For Environmental Review Of Marshfield Safe Drinking Water Loan Program Project
Dec 11th, 2024 by Wisconsin Department of Natural ResourcesGroundbreaking Production Coming to Historic Third Ward January 2025
DNR Releases 2024 Air Quality Trends Report
Dec 10th, 2024 by Wisconsin Department of Natural ResourcesIncludes Air Monitoring Data Through 2023